Under Slab Plumbing is Complete

March 23, 2023 47308 Views

PART 3- Full video is posted on our channel.

After inspection I use my laser level to mark the top of the concrete floor on the drain then the plumbers cut an additional inch off. This way after they glue the drain on it will be a ½” lower than the floor.
We cover the drains with tape, so no concrete gets in them.
I take my rake and start filling in around the pipes- I had left all the joints uncovered for the inspector to see. That we he knew everything was primed and glued.
I used my Ventrac to get rid of some of the bigger rocks that were in the way, and brought a couple scoops of gravel back to fill in where dirt had been taken out.
Everything is graded back level and smooth- now we’re ready to put down vapor barrier and rebar. @hausplans

#build #building #howto #underslab #plumbing #construction #diy #contractor #concrete